Purchase Solution

Status Report

Not what you're looking for?

Ask Custom Question

Status Report:

Task A: Budgeted work/cost 120 hours/$1200, Actual work cost to date60 hours/$600, percent of work complete 30%, Estimate to complete 90 hours/$900, planned start March 15, planned end date June 15, actual start date March 30, projected end date June 15, planned resource utilization 25%, actual resource utilization 30%.

Task B: Budgeted work cost 120 hours/$1200, Actual work cost to date50 hours/$500, percent of work complete 30%, Estimate to complete 60 hours/$600, planned start April 1, planned end date May 15, actual start date April 8, projected end date May 30, planned resource utilization 50%, actual resource utilization 30%.

You review her status report for mailing activities and determine that Jennifer doesn't have a solid grasp of her status. Ben was unable to provide you with anything more than "Things are moving along just fine." Using earned value measurements along with the other information and metrics available, determine the true status of Jennifer's portion of the project. Prepare an updated status report (one page) for Jennifer and share the measurements and your rationale in your determination of the status for the project. Create a two to three slide presentation explaining the benefits of using EVM. Be sure to document some instructions (one page document) for Jennifer and Ben for determining the project status for their next project update to you.

Purchase this Solution

Solution Summary

The response addresses the queries posted in 730 words with references and a ppt.

Solution Preview

Please find the file attached.

Earned Value Measurement: Status Report

Status Report
The model of Earned Value Measurement can be used to determine the true status of the project. The EVM model has three key elements or metrics namely the planned value, the earned value and the actual cost, which form the basis for the Earned Value Measurement. These three values should be first determined in order to know about the Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI) and Cost Performance Index (CPI) (Project Management).
For the project, we will determine the value of these three elements i.e. planned value, the earned value and the actual cost. The Planned Value (PV) is also known as the Budgeted Cost of Work Schedule (BCWS), the Earned Value is also known as the Budgeted Cost of Work Performed (BCWP) and the Actual Cost is also known as the Actual Cost of Work Performed (ACWP) (Use Earned Value Management (EVM) to determine project status, 2007).
For Task A, the three metrics are as follows:
PV = $1200
EV = $360
AC = $600
Therefore, the four variances ...

Solution provided by:
Education
  • MBA (IP), International Center for Internationa Business
  • BBA, University of Rajasthan
Recent Feedback
  • "Thank You so much! "
  • "Always provide great help, I highly recommend Mr. Sharma over others, thanks again. "
  • "great job. I will need another help from you. "
  • "first class!"
  • "Thank you for your great notes. Will you be willing to help me with one more assignment? "
Purchase this Solution


Free BrainMass Quizzes
Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.