3. Determine the cost/day for each activity and complete the time-Cost trade-off function for the various possible plans.
Immediate TIME COST
Activity Predecessor Normal Crash Normal Crash Cost/Day
A --- 7 6 $400 $460
B A 5 3 500 600
C A 4 2 600 780
D B 3 1 200 320
E C 6 3 500 710
F D,E 6 5 500 630
Plan Time Cost
1
Purchase this Solution
Solution Summary
The solution determines the cost/day for each activity. The Time-Cost trade-off function for the various possibilities is determined.
Solution Preview
See the attached file. Thanks
3. Determine the cost/day for each activity and complete the time-Cost trade-off function for the various possible plans.
Immediate TIME COST
Activity Predecessor Normal Crash Normal Crash Crash Cost/Day
A --- 7 6 $400 $460 $60
B A 5 3 500 600 $50
C A 4 2 600 780 $90
D B 3 1 200 320 $60
E C 6 3 500 710 $70
F D,E 6 5 500 630 $130
First draw the network diagram:
The critical path is ACEF and the normal project completion time is 23 days.
The other path is ABDF with a time length of 21 days.
Using normal time, the slack analysis for the project is as below
Activity On Critical Activity Earliest Earliest Latest Latest Slack
Name Path Time Start Finish Start Finish (LS-ES)
1 A Yes 7 0 7 0 7 0
2 B no 5 7 12 9 14 2
3 C Yes 4 7 11 7 11 0
4 D no 3 12 15 14 17 2
5 E Yes 6 11 17 11 17 0
6 F Yes 6 17 23 17 23 0
Project Completion Time = 23 Days
Total Cost of Project = $2,700
Since the next longest path (after the Critical path) is 21 days long, we can crash upto 2 days without changing the critical path. On the critical path, the minimum cost of crashing per day is for activity at at$60 per day. So we should crash the activity ...
Purchase this Solution
Free BrainMass Quizzes
Transformational Leadership
This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.
Understanding Management
This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.
Understanding the Accounting Equation
These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.
Six Sigma for Process Improvement
A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.