Assume that an activity has a normal tune of 20 weeks, a normal cost of $72,000, a crash time of 16 weeks, and a crash cost of $100,000. By how many weeks, at most, can this activity's duration be reduced? What is the cost per week to accelerate this activity?

Solution Preview

We know that an activity cannot be completed in less than its crash time.

So, maximum ...

Solution Summary

Solution determines the cost per week to accelerate the given activity.