Case Study: Sharp Printing, AG: Differences in a macro and micro estimate for a project

See attached Case Study: Sharp Printing, AG

This is a classic example of the differences between a macro and micro estimate. You are the project manager and need to respond. What would you do? What might be some of the reasons why the macro estimate is off? For what reasons should you trust the micro estimate as being more reliable than the macro estimate?