Become a Member
 

Probability of Completion of a Project

The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of 4 weeks.

A) What is the probability the project will be finished in 62 weeks or less?
B) What is the probability the project will be finished in 66 weeks or less?
C) What is the probability the project will take longer than 65 weeks?

Solution Summary

Probability of Completion of a Project whose time to completion is normally distributed has been calculated.

$2.19
This answer includes:
  • Plain text
  • Cited sources when necessary
  • Attached file(s)
    • 342842-statistics-normal distribution.xls
Add to Cart   $2.19