Quantitative analysis:Networks, PERT, critical path.
Not what you're looking for?
A project has the following precedence realationship and activity times
Activity Activity Time Immediate Predecessors
A 4 -
B 10 -
C 5 A
D 15 B, C
E 12 B
F 4 D
G 8 E
H 7 F,G
A. Draw a Network Diagram
B. Calculate the slack for each activity, Which Activity are on the Critical path
The following information is available about a project
Activity Activity Time Immediate Predecessors
A 3 -
B 4 -
C 5 -
D 4 -
E 7 A
F 2 B,C, D
G 4 E, F
H 6 F
I 4 G
J 3 G
K 3 h
A. Draw a Network Diagram
B. Find the critical Path
The following information has been gathered about a project
Activity Activity Time Immediate Predecessors
A 4 -
B 7 A
C 9 B
D 3 B
E 14 D
F 10 C, D
G 11 F, E
A. Draw a Network Diagram
B. Calculate the slack for each activity and determine the critical path. How long with the project take.
Purchase this Solution
Solution Summary
The problem set deals with issues in quantitative analysis: Critical paths, PERT charts, slack etc.
Education
- B. Sc., University of Nigeria
- M. Sc., London South Bank University
Recent Feedback
- "Thank you."
- "thank you Chidi Ngene.. if you have any APA references would be great"
- "Thank you so much for your help, your explanations were easy to understand and apply!"
- "are you able to highlight the equations used either on the xlsx or a word doc as to how each graph was formed- overall looks fine i just need help understanding this myself"
- "Chidi Ngene, M. Sc. Was extremely helpful as without the help and guidance I would have failed, but with the help I passed. I still have a lot to learn and in need of the guidance to understand and learn more on the subject. I would recommend Chidi Ngene and BrainMass to anyone that are in need of help. Thank you!!"
Purchase this Solution
Free BrainMass Quizzes
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.
Managing the Older Worker
This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce
MS Word 2010-Tricky Features
These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Employee Orientation
Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.