A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day ________ (rounded to nearest day).
a) 833
b) 807
c) 1009
d) 689
e) 631
Explain in one sentence why please
Purchase this Solution
Solution Summary
The solution calculates the number of days in which the project will be calculated with a 20% probability.
Solution Preview
A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will ...
Purchase this Solution
Free BrainMass Quizzes
MS Word 2010-Tricky Features
These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.
Transformational Leadership
This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.
Employee Orientation
Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.
Income Streams
In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.
Production and cost theory
Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.