Pert Problem of Critical Path

Not what you're looking for?

Ask Custom Question

The pert problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before?

1. 118
2. 115
3. 109
4. 108
5. 98

Purchase this Solution

Solution Summary

The solution uses a critical path to determine what the 0.9 probability is that the project will be completed before.

Solution Preview

For P=0.90, first get the value of Z from standard normal distribution table. The ...

Purchase this Solution


Free BrainMass Quizzes
Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations

Basics of corporate finance

These questions will test you on your knowledge of finance.

Introduction to Finance

This quiz test introductory finance topics.